Which of the following project requirements must be met before the project can be handed over to the Technical Consultant team? There are 2 correct answers to this question.

Which of the following project requirements must be met before the project can be handed over to the Technical Consultant team? There are 2 correct answers to this question.
A . Discrepancy reporting must be completed
B. The extract scripts have been developed and tested, if applicable for the data source
C. Beta Site is verified by the customer
D. The Specification Document quality gate has been completed

Answer: B, D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments