Which of the following project requirements must be met before the project can be handed over to the Technical Consultant team? There are 2 correct answers to this question.

Which of the following project requirements must be met before the project can be handed over to the Technical Consultant team? There are 2 correct answers to this question.
A . Discrepancy reporting must be completed
B . The extract scripts have been developed and tested, if applicable for the data source
C . Beta Site is verified by the customer
D . The Specification Document quality gate has been completed

Answer: B,D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments