Which of the following project management tools would help?
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed .
Which of the following project management tools would help?
A . Issue log
B . Project charter
C . Dashboard
D . Meeting minutes
Answer: D