Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.
A . Planned order
B. Purchase order
C. Delivery schedule line
D. Purchase requisition

Answer: C,D