Which of the following PRINCE2 processes includes creating the project plan?
Which of the following PRINCE2 processes includes creating the project plan?
A . Starting up a project
B . Initiating a project
C . Managing product delivery
D . Directing a project
Answer: B
Explanation:
According to PRINCE2, a project management methodology, the process of initiating a project includes creating the project plan, which is a high-level plan that covers the whole project scope, schedule, budget, quality, and risks. The project plan is based on the project brief, the business case, and the product descriptions. The project plan is used to obtain the authorization from the project board to initiate and execute the project. The project plan is also refined and updated throughout the project life cycle as more information becomes available.
The other processes are not directly involved in creating the project plan. Starting up a project is a pre-project process that ensures the project is viable and worthwhile, and produces the project brief
and the initiation stage plan. Managing product delivery is a process that coordinates the delivery of products from the team managers to the project manager, and ensures that the work conforms to the quality criteria and the project plan. Directing a project is a process that enables the project board to oversee and control the project, and make key decisions and approvals.
Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 5: Project Scope Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 5: Project Scope Management2; PRINCE2 Processes – 7 Processes Of PRINCE2 Explained3; Initiating a Project Process – This process i s the procedure which defines the product quality, Project Product, project timeline, costs, the commitment of resources, risk analysis, and assembles the Project Initiation Documentation (PID)4
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund