Which of the following primary factors are used to prioritize the development of risk response strategies? ( Choose two.)
Which of the following primary factors are used to prioritize the development of risk response strategies? ( Choose two.)
A . Likelihood
B . Timeline
C . Impact
D . Quality
E . Cost
Answer: A,C