A . The shelf life expiration date check is activated for the material type in Customizing.
B. The purchase order item contains the remaining shelf life.
C. The total shelf life is maintained in the purchasing info record.
D. The shelf life expiration date check is activated for the movement type in Customizing.

Answer: B,D