Which of the following planning settings can be done for a replenishment order? Note: There are 2 correct answers to this question.

Which of the following planning settings can be done for a replenishment order? Note: There are 2 correct answers to this question.
A . Allow suppliers to send planned replenishment
B . Allow suppliers to edit price
C . Allow supplier to edit gross demand
D . Allow replenishment horizon in weeks

Answer: A,B