A number of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.

i) External test specialists perform non-functional testing.

ii. Testing is outsourced.

iii. Testing is carried out by the developer.

iv. A separate test team carries out the testing.

v) Testing is performed by the business.

vi. Testing is performed by a different developer.

Which of the following orders the above in a correct order of independence? 1 credit
A . i, ii, iv, vi
B . ii, i, v, vi
C . ii, v, i, iii
D . i, iv, v, vi

Answer: B