Which of the following options BEST describes Request for Quote (RFQ)?
Which of the following options BEST describes Request for Quote (RFQ)?
A . Usually provides more detail involved with selecting the material, equipment, and components required during implementation (e.g. make, model, performance specifications)
B . Can be submitted by the contractor in response to a field order or as an uninitiated request for a change in scope
C . Used to obtain a formal response to the contract documents
D . An invitation for the design professionals (e g, architect, engineer, consultant) or contractors to submit a proposal for services
Answer: A