- All Exams Instant Download
Which of the following must be in place before implementing a BCP?
Which of the following must be in place before implementing a BCP?
A . SLA
B. AUP
C. NDA
D. BIA
Answer: D
Explanation:
A Business Impact Analysis (BIA) is a critical component of a Business Continuity Plan (BCP). It identifies and prioritizes critical business functions and determines the impact of their disruption.
Latest SY0-601 Dumps Valid Version with 396 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments