Which of the following must be completed before the change can be approved?
An administrator has submitted a change request for an upcoming server deployment.
Which of the following must be completed before the change can be approved?
A . Risk analysis
B. Sandbox testing
C. End user acceptance
D. Lessons learned
Answer: A
Explanation:
A risk analysis must be completed before a change request for an upcoming server deployment can be approved 1
Risk analysis is an important step in the change management process because it helps identify and mitigate potential risks before changes are implemented. Once the risks have been analyzed and the appropriate measures have been taken to minimize them, the change can be approved and implemented.
Latest 220-1102 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments