Which of the following MOST likely needs to be analyzed before rehosting the ERP?

A company needs to rehost its ERP system to complete a datacenter migration to the public cloud.

The company has already migrated other systems and configured VPN connections.

Which of the following MOST likely needs to be analyzed before rehosting the ERP?
A . Software
B. Licensing
C. Right-sizing
D. The network

Answer: C