Which of the following milestones represent a DA project moving from Construction to Transition stage?
A . Sufficient functionality
B. Stakeholder vision
C. Continued viability
D. Proven architecture
E. Production ready
Answer: A
Explanation:
When sufficient functionality is built, the project moves into transition phase