Exam4Training

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Which of the following might the Scrum Team discuss during a Sprint Retrospective?
A . Methods of communication.
B . The way the Scrum Team does Sprint Planning.
C . Skills needed to improve the Development Team’s ability to deliver.
D . Its Definition of “Done”.
E . All of the above.

Answer: E

Explanation:

The correct answer is E, because all of these topics can be discussed during a Sprint Retrospective. The Scrum Guide states that “the purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. … During each Sprint Retrospective, the Scrum Team plans ways to improve product quality by adapting the definition of ‘Done’ as appropriate.” Therefore, the Scrum Team can discuss any aspect of their process, communication, skills, or definition of ‘Done’ that may help them improve.

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version