Which of the following might be consequences of over-specification? Select TWO that apply:
Which of the following might be consequences of over-specification? Select TWO that apply:
A . Reducing motion waste
B . Higher cost due to inessential features
C . Limiting competition in supply market
D . Lack of essential features
E . Better contract management
Answer: B, D
Explanation:
Over-specification can cause problems to buying organisation, include the following:
– Higher expense due to unnecessary features embedded into the product
– Stifle competition because higher requirements will lead to fewer suppliers in the market are able to supply
– Harder to evaluate the trade-offs between different features and attributes in the specification
Reference: CIPS study guide page 141-142