Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
A . EAC
B . BAC
C . CPI
D . ETC
Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments