Which of the following measures would a project manager use to assess the team’s progress against the project schedule?
Which of the following measures would a project manager use to assess the team’s progress against the project schedule?
A . Function point metric
B . Earned value analysis
C . SMART metrics
D . COCOMO H Model
Answer: B
Explanation:
Earned Value Analysis (EVA) is a project management technique used to measure project performance and progress. It integrates project scope, time, and cost data to provide accurate forecasts of project performance.
Planned Value (PV): The estimated value of work planned to be done.
Earned Value (EV): The value of work actually completed.
Actual Cost (AC): The actual cost incurred for the completed work.
Using these metrics, EVA can help project managers assess whether they are ahead or behind schedule and within or over budget.
Reference: "Project Management: A Systems Approach to Planning, Scheduling, and Controlling" by Harold Kerzner
PMBOK Guide by Project Management Institute (PMI)