Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
A . EAC
B . BAC
C . TCPI
D . ETC

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232