Which of the following job roles is primarily tasked with communicating the project timeline changes?

Which of the following job roles is primarily tasked with communicating the project timeline changes?
A . Project scheduler
B . Project manager
C . Project sponsor
D . Project coordinator

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 93