Which of the following is your BEST course of action?

After construction on a project has begun, the client asks you to change the wallcovering originally specified to one that does not meet current code requirements.

Which of the following is your BEST course of action?
A . Research available products that are similar to the requested product and meet the code requirements. Present the options to the client for approval.
B . Write a letter to the client stating that the change is against your professional recommendation and that you will make the change but assume no liability.
C . Write a letter to the client explaining that you will not make the requested change.
D . Tell the client that you will remove the wallcovering from the project and that the client may select and install a different product after your work is completed.

Answer: A