Which of the following is TRUE about most project life cycles?

Which of the following is TRUE about most project life cycles?
A . Staffing level is highest at the start.
B . The stakeholders’ influence is highest at the start.
C . The level of uncertainty is lowest at the start.
D . The cost of changes is highest at the start.

Answer: B