Exam4Training

Which of the following is the ordei of priority for risk mitigation from highest to lowest?

An organization has the following risk mitigation policies

• Risks without compensating controls will be mitigated first it the nsk value is greater than $50,000

• Other nsk mitigation will be pnontized based on risk value.

The following risks have been identified:

Which of the following is the ordei of priority for risk mitigation from highest to lowest?
A . A, C, D, B
B. B, C, D, A
C. C, B, A, D
D. C, D, A, B
E. D, C, B, A

Answer: C

Explanation:

The order of priority for risk mitigation from highest to lowest is C, B, A, D.

This order is based on applying the risk mitigation policies of the organization. According to the first policy, risks without compensating controls will be mitigated first if the risk value is greater than $50,000. Risk C has no compensating controls and a risk value of $75,000, so it is the highest priority. Risk B also has no compensating controls, but a risk value of $40,000, so it is the second priority. According to the second policy, other risk mitigation will be prioritized based on risk value. Risk A has a risk value of $60,000 and a

compensating control of encryption, so it is the third priority. Risk D has a risk value of $50,000 and a compensating control of backup power supply, so it is the lowest priority.

Latest CS0-002 Dumps Valid Version with 220 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version