Which of the following is the NEXT step?
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
A . Implementation
B . Approval
C . Validation
D . Auditing
Answer: B
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294