Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A . 12 days
B . 14 days
C . 16 days
D . 19 days
Answer: A
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 169
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments