Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
A . Project manager and project scheduler
B . Project coordinator and project sponsor
C . Project champion and project scheduler
D . Project stakeholders and project team
Answer: D
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326