A change advisory board just approved a change request.
Which of the following is the MOST likely next step in the change process?
A. End user acceptance
B. Perform risk analysis
C. Communicate to stakeholders
D. Sandbox testing
Answer: C
Explanation:
A. End user acceptance – While this is an important part of the process, it typically comes later, after the change has been implemented and tested.
B. Perform risk analysis – This is a crucial part of the change management process, but it would typically be done before the change request is approved by the change advisory board, not after.
C. Communicate to stakeholders – Once a change has been approved by the change advisory board, the next step is typically to communicate this decision to the relevant stakeholders. This is to ensure everyone affected by the change is aware of it, understands what will happen, and knows the timeline for the change.
D. Sandbox testing – While testing is an important part of the change management process, it’s not the immediate next step after approval. Before you can begin testing, you need to communicate the planned changes to all relevant parties.
Therefore, the most likely next step in the change process after the approval is to communicate the change to the stakeholders.