Which of the following is the MOST likely next step in the change process?
A change advisory board just approved a change request.
Which of the following is the MOST likely next step in the change process?
A . End user acceptance
B . Perform risk analysis
C . Communicate to stakeholders
D . Sandbox testing
Answer: D