While monitoring an enterprise’s IT projects portfolio, it is discovered that a project is 75% complete, but all budgeted resources have been expended.
Which of the following is the MOST important task to perform?
A . Review the IT investments.
B . Reorganize the IT projects portfolio.
C . Re-evaluate the business case.
D . Review the IT governance structure.
Answer: C
Latest CGEIT Dumps Valid Version with 413 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund