Which of the following is the MOST important task to perform?

While monitoring an enterprise’s IT projects portfolio, it is discovered that a project is 75% complete, but all budgeted resources have been expended.

Which of the following is the MOST important task to perform?
A . Review the IT investments.
B . Reorganize the IT projects portfolio.
C . Re-evaluate the business case.
D . Review the IT governance structure.

Answer: C