Which of the following is the MOST important input for prioritizing resources during program initiation?
A . Replacement cost
B . Risk register
C . Business impact assessment
Answer: C
Explanation:
A business impact assessment (BIA) is the most important input for prioritizing resources during program initiation, because it helps to identify and evaluate the potential effects of disruptions to critical business functions and processes12. A BIA can help to determine the recovery objectives, priorities, and strategies for the program, as well as the resource requirements and dependencies34.
Reference: 1: Business Impact Analysis | Ready.gov 2: Business Impact Analysis – ISACA 3: COBIT 2019 Implementation Guide 4: COBIT 2019 Implementation – ISACA