Which of the following is the MOST effective method for providing these updates?

A project requires daily status updates.

Which of the following is the MOST effective method for providing these updates?
A . Backlog
B . Standup
C . Kickoff
D . Retrospective

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306