Which of the following is the last step of the cycle?
Risk Management is a process with several steps.
Which of the following is the last step of the cycle?
A . identify risks
B. treat
C. monitor and review
D. communicate and consult
Answer: C
Explanation:
monitor and review is the last stage. The full cycle is; establish context – identify risks – analyse and evaluate risks – treat -communicate and consult – monitor and review. See p. 142