Exam4Training

Which of the following is the ideal solution for management in this scenario?

Management is designing its disaster recovery plan. In the event that there is significant damage to the organization’s IT systems this plan should enable the organization to resume operations at a recovery site after some configuration and data restoration.

Which of the following is the ideal solution for management in this scenario?
A . A warm recovery plan.
B . A cold recovery plan.
C . A hot recovery plan.
D . A manual work processes plan

Answer: C