Exam4Training

Which of the following is the FINAL step to be performed prior to promoting to production?

A systems engineer is building a new system for production.

Which of the following is the FINAL step to be performed prior to promoting to production?
A . Disable unneeded services.
B. Install the latest security patches.
C. Run a vulnerability scan.
D. Encrypt all disks.

Answer: C

Explanation:

Running a vulnerability scan is the final step to be performed prior to promoting a system to production. This allows any remaining security issues to be identified and resolved before the system is put into production.

Latest SY0-601 Dumps Valid Version with 396 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version