Which of the following is the correct sequence for the above tasks?
While developing a project schedule, the project manager is attempting to sequence the following tasks:
Which of the following is the correct sequence for the above tasks?
A . F, C, A, E, B, D
B . F, E, C, B, A, D
C . F, A, B, C, E, D
D . D, B, E, F, C, A
Answer: B