Exam4Training

Which of the following is the correct order in the risk management phase?

Management decides to implement a risk management system to reduce and maintain the organization’s risk at an acceptable level.

Which of the following is the correct order in the risk management phase?
A . Risk Identification, Risk Assessment, Risk Treatment, Risk Monitoring & Review
B . Risk Treatment, Risk Monitoring & Review, Risk Identification, Risk Assessment
C . Risk Assessment, Risk Treatment, Risk Monitoring & Review, Risk Identification
D . Risk Identification. Risk Assessment. Risk Monitoring & Review, Risk Treatment

Answer: A

Latest 312-38 Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version