Due to cost constraints, the company postponed the replacement date for supporting core application hardware.
Which of the following is the biggest risk?
A . The final replacement cost may be higher
B . System availability may be affected
C . Maintenance costs may increase
D . May not be upgraded in the future
Answer: B