Which of the following is the BEST risk response strategy?
A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.
Which of the following is the BEST risk response strategy?
A . Exploit
B . Enhance
C . Mitigate
D . Communicate
Answer: C