Which of the following is the BEST project management methodology for this requirement?
A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?
A . Waterfall
B . Agile
C . PRINCE2
D . Bottom-up
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310