Which of the following is the BEST explanation?
A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon.
Which of the following is the BEST explanation?
A . In the beginning, projects entail a degree of uncertainty that needs to be specified.
B . In the beginning, projects have start and finish dates that require elaboration.
C . In the beginning, projects are part of a program that requires coordination.
D . In the beginning, projects start with detailed inputs that need to be explained.
Answer: A