A technician is installing a variety of servers in a rack.
Which of the following is the BEST course of action for the technician to take while loading the rack?
A . Alternate the direction of the airflow
B . Install the heaviest server at the bottom of the rack
C . Place a UPS at the top of the rack
D . Leave 1U of space between each server
Answer: B
Explanation:
The technician should install the heaviest server at the bottom of the rack to load the rack properly. Installing the heaviest server at the bottom of the rack helps to balance the weight distribution and prevent the rack from tipping over or collapsing. Installing the heaviest server at the bottom of the rack also makes it easier to access and service the server without lifting or moving it. Installing the heaviest server at any other position in the rack could create instability and safety hazards.