Which of the following is required to enable tape parallel processing?
Which of the following is required to enable tape parallel processing?
A . The source repository for the tape job is a scale out backup repository.
B. The tape library has multiple drives.
C. Two tape jobs are processed at the same time.
D. The tape drive has multiple tapes.
Answer: B