Which of the following is required for an organization to properly manage its restore process in the event of system failure?
Which of the following is required for an organization to properly manage its restore process in the event of system failure?
A . IRP
B . DRP
C . RPO
D . SDLC
Answer: B
Explanation:
A disaster recovery plan (DRP) is a set of policies and procedures that aim to restore the normal operations of an organization in the event of a system failure, natural disaster, or other emergency. A DRP typically includes the following elements:
A risk assessment that identifies the potential threats and impacts to the organization’s critical assets and processes.
A business impact analysis that prioritizes the recovery of the most essential functions and data. A recovery strategy that defines the roles and responsibilities of the recovery team, the resources and tools needed, and the steps to follow to restore the system.
A testing and maintenance plan that ensures the DRP is updated and validated regularly. A DRP is required for an organization to properly manage its restore process in the event of system failure, as it provides a clear and structured framework for recovering from a disaster and minimizing the downtime and data loss.
Reference = CompTIA Security+ Study Guide (SY0-701), Chapter 7: Resilience and Recovery, page 325.