Which of the following is not an output of a critical path analysis?
Which of the following is not an output of a critical path analysis?
A . Total and free float.
B . Earliest start time and latest finish time of activities.
C . Project completion time.
D . Cost-benefit analysis.
Answer: D
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments