Which of the following is NOT an objective of a Retrospect Sprint Meeting?

Which of the following is NOT an objective of a Retrospect Sprint Meeting?
A . Identify process improvements
B . Identify best practices
C . Identify new product features
D . Identify process problems and bottlenecks

Answer: C

Explanation:

Primary objectives of the meeting are to identify three specific things:

– Things the team needs to keep doing: best practices

– Things the team needs to begin doing: process improvements

– Things the team needs to stop doing: process problems and bottlenecks

– These areas are discussed and a list of Agreed Actionable Improvements is created.

Reference: http://blog.scrumstudy.com/all-about-retrospect-sprint-meeting/