Which of the following is NOT an end goal of BOTH quality improvement programs and continuous process improvement?

Which of the following is NOT an end goal of BOTH quality improvement programs and continuous process improvement?
A . Achieving a specific set goal
B . Reducing errors and defects
C . Improving efficiency
D . Improving profits

Answer: D