Which of the following is not about Fit/Gap Analysis (done during Explore Phase)? There are 2 answers to this question.

Which of the following is not about Fit/Gap Analysis (done during Explore Phase)? There are 2 answers to this question.
A . Validate pre-activate and pre-assembled solution in the development system.
B. Drive towards adopting customers processes.
C. Minimize the needs for rework during realization.
D. Prioritize delta requirement and gaps.

Answer: A,B