Which of the following is NOT a valid reason for a planned break between stages?

Projects carried out using the PRINCE2 methodology are always set out in a series of distinct and sequential stages.

Which of the following is NOT a valid reason for a planned break between stages?
A . The project team is required to break and regroup ready for the next package of work.
B . The project board can make a decision as to whether the project business case is still viable.
C . The progress of the project can be reviewed to ensure this justifies the continuation of the project.
D . Risks to the project can be reassessed before further commitments of money or resources.

Answer: A

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments