Which of the following is NOT a Scrum Master’s responsibility?

Which of the following is NOT a Scrum Master’s responsibility?
A . Groom the Prioritized Product Backlog.
B . Coordinate creation of Release Planning Schedule.
C . Facilitate Prioritized Product Backlog Review Meetings.
D . Represent the Scrum Core Team to provide lessons from the project.

Answer: A

Explanation:

The prime responsibilities of a Scrum Master are:

– Removes the obstacles/impediments that affect productivity.

– Shields the people from external disturbance.

– Responsible if the scrum process is correctly applied.

– Facilitate daily stand-ups, other ceremonies, schedule meetings, demo and other meetings.

– Help product owner in prioritizing the backlog and any feedback from the team.

– Facilitation of Retrospective meetings

– Workshops for planning, estimation, prioritization, issue resolution, performance improvements

Reference: https://www.knowledgehut.com/interview-questions/scrum