Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?

A town has begun a project that involves keeping track of the buses traveling on the roads of the town.

Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?
A . Detailed upfront planning will be done to ensure that risks are identified early on.
B . The team working on this project will meet every day for 15 minutes to list impediments to completing their tasks.
C . The Product Owner will prioritize the tasks that deliver maximum business value.
D . The customer does not have to be able to define very concrete requirements early on.

Answer: B